Microsoft 70-178 Exam : Microsoft Project 2010, Managing Projects

Microsoft 70-178 exam
  • Exam Code: 70-178
  • Exam Name: Microsoft Project 2010, Managing Projects
  • Updated: Sep 21, 2026
  • Q & A: 70 Questions and Answers
Already choose to buy "PDF"
Price: $59.99 

About Microsoft 70-178 Exam Questions

Fast Delivery in 5-10 Minutes

It's wildly believed that time is gold among city workers. People are all hunger to get the products immediately after purchasing in this high-speed time. As an electronic product, our 70-178 free pdf dumps have the character of fast delivery. Candidates would receive the 70-178 verified answers & questions in 5-10 minutes through their email after successful pavement. We check about your individual information like email address and the 70-178 : Microsoft Project 2010, Managing Projects valid test dumps to avoid mistakes in just a few minutes and you can start your reviewing at once. Please email to us if you have any question, we will answer your question about 70-178 practice torrent dumps and help you pass the exam smoothly. So choose us, choose high efficiency.

Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)

PDF Version

Our 70-178 verified study torrent can be downloaded into three types, namely PDF Version, SOFT (PC Test Engine) Version and APP (Online Test Engine) Version. When it comes to other some negative effects accompanied by the emergence of electronic equipments like eyestrain, some people may adopt the original paper study. We take this situation into consideration, as for the PDF Version, it's easy for you to read and print, candidates can rely on printed Microsoft 70-178 exam PDF to review. Furthermore, it's easy to take notes. You can write down you notes beside the unclear knowledge points or the questions you have answered incorrectly, thus your next reviewing would be targeted. By this high efficient reviewing 70-178 verified study torrent, candidates will benefit a lot in short term and pass exam quickly.

In recent years, the majority of all countries have achieved preeminent progress thanks to the widespread Internet and developed society industry (70-178 latest exam dumps). This trend also resulted in large groups of underprivileged people who lack in computer skills. These people find it difficult to find a satisfactory job (70-178 verified study torrent), and many of them are likely to turn to unemployment. In a word, this tendency raises the requirement for many employees, especially for working persons. So what can you do to make yourself outstanding? An Microsoft certificate would be you shining point and it's also an important element for your employer to evaluate you. So how could you pass the 70-178 easily? Our Microsoft Project 2010, Managing Projects practice torrent dumps would be your best choice.

Free Download Pass 70-178 Exam Cram

High-accuracy 70-178 verified study torrent

For many candidates, preparing for the 70-178 exam will take time and energy, and therefore choosing a right 70-178 verified answers & questions are vital for candidates. If you choose our Microsoft verified study torrent to review, you will find obtaining the certificate is not so difficult. The most important function of a 70-178 verified study torrent must be high accuracy fits with the 70-178 exam, which is also our most clipping advantage. Our 70-178 verified study torrent is very comprehensive and includes the latest exam content. On one hand we provide the latest questions and answers about the Microsoft 70-178 exam, on the other hand we update our 70-178 verified study torrent constantly to keep the accuracy of the questions. Our high accuracy ensure high pass rate which has reached 99%, so you can totally trust us, trust our 70-178 valid test dumps.

Microsoft 70-178 Exam Syllabus Topics:

SectionObjectives
Topic 1: Initiating Projects- Defining project scope and objectives
  • 1. Identify stakeholders and requirements
    • 2. Establish project goals and constraints
      Topic 2: Executing Projects- Project execution tracking in Microsoft Project
      • 1. Task progress monitoring
        • 2. Baseline comparison
          Topic 3: Closing Projects- Project closure activities
          • 1. Final reporting and documentation
            • 2. Lessons learned documentation
              Topic 4: Monitoring and Controlling Projects- Schedule and performance control
              • 1. Reporting and dashboards
                • 2. Variance analysis
                  - Managing changes
                  • 1. Updating schedules and rebaselining
                    Topic 5: Planning Projects- Resource planning and allocation
                    • 1. Resource assignment and leveling
                      • 2. Cost and budget planning
                        - Project scheduling and task planning in Microsoft Project 2010
                        • 1. Work Breakdown Structure (WBS) creation
                          • 2. Critical path analysis
                            • 3. Task dependencies and constraints

                              Microsoft Project 2010, Managing Projects Sample Questions:

                              Question #1

                              You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?

                              • A. On the Display tab of the Project options, clear the Edits to start and finish dates check box.
                              • B. Click New Tasks and change the option to Auto Scheduled.
                              • C. On the Schedule tab of the Project options, change the New tasks created option to Manually Scheduled.
                              • D. Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.
                              • E. On the Advanced tab of the Project options, clear the Automatically add new resources and tasks check box.
                              Reveal Solution  Discussion  0

                              Correct Answer: C  🗳️

                              Question #2

                              All tasks are assigned to multiple team members. A business analyst sends you an e-mail message that contains the dates of her vacation. You need to modify the schedule to reflect delays that are caused only by the business analysts vacation dates. What should you do?

                              • A. Use the Mark on Track command.
                              • B. Modify the start and end dates of all the tasks of the business analyst.
                              • C. Change the working time for the resource calendar of the business analyst.
                              • D. Create a new enterprise calendar, and then enter the vacation days.
                              Reveal Solution  Discussion  0

                              Correct Answer: C  🗳️

                              Question #3

                              You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?

                              • A. Set the Finish date field.
                              • B. Set the Deadline date field.
                              • C. Select the Mark task as milestone check box.
                              • D. Set the Constraint date field.
                              • E. Select the Display on Timeline check box.
                              Reveal Solution  Discussion  0

                              Correct Answer: B  🗳️

                              Question #4

                              You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?

                              • A. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, and then click OK.
                              • B. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Entire project radio button, and then click OK.
                              • C. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
                              • D. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
                              Reveal Solution  Discussion  0

                              Correct Answer: D  🗳️

                              Question #5

                              You use Project Professional 2010 to manage a software development project as shown in the exhibit. (Click the Exhibit button.)

                              You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

                              • A. Inactivate the task.
                              • B. Create a link from the Develop functional specifications task to the Review functional specifications task.
                              • C. Make the task 100 percent complete.
                              • D. Set the tasks remaining work to 0 hours.
                              • E. Delete the task.
                              Reveal Solution  Discussion  0

                              Correct Answer: B,E  🗳️

                              What Clients Say About Us

                              I bought the 70-178 exam materials from VerifiedDumps and my friend bought from the other website, now i passed my exam, but he failed. He will buy your 70-178 exam materials as well. Both of us believe in your website-VerifiedDumps!

                              Enid Enid       4.5 star  

                              Today, i am in a very good mood. You know why? For i have just taken my 70-178 examination and passed it. Thanks for your support!

                              Brook Brook       5 star  

                              Thank you!
                              Yes, I passed 70-178.

                              Bblythe Bblythe       4 star  

                              Thanks VerifiedDumps! I found the 70-178 answers given accurate and relevant! I suggest the candidates to try out the practice test. surely, they will score great marks like me.

                              Sylvia Sylvia       4.5 star  

                              Passed the 70-178 exam yesterday! I bought the Value Pack since the price is so much cheaper than the other websites, and these three versions give me more joyful study experice. You gays can buy the same with me.

                              Nora Nora       5 star  

                              I am sure that I would make a great hit in 70-178 exam with the help of 70-178 exam practice test.

                              Amos Amos       5 star  

                              Oh my god! That's awesome, just passed 70-178 exam with super high score as 99% points for like 80 minutes. Thanks!

                              Astrid Astrid       4.5 star  

                              I just write to tell you that i passed the 70-178 exam with your help. I am really fond of you. You gays are so kind and considerate. Thank you so much!

                              Evan Evan       5 star  

                              I failed my exam with other website dumps. I think these website has the latest 70-178 dump. I remember the new questions. They are in this dump! PASSED SUCCESSFULLY!

                              Richard Richard       4.5 star  

                              You use the real talent and explores it in
                              right way ,and this is actually an ultimate source for the sake of preparing 70-178 exam.

                              Owen Owen       4 star  

                              Worthy of buying the 70-178 training guide, i was at a loss before i owned it.

                              Max Max       4 star  

                              I got the certificate by using the 70-178 study guide materials of VerifiedDumps, and now my position has improved in my company, and I have more spare time now.

                              Sandy Sandy       4.5 star  

                              I am glad that I passed my 70-178 examination today. I really appreciate the accurate 70-178 practice questions because i didn’t have enough time to prepare for the exam. But, with the help of your exam dump, I passed it. Thank you very much!

                              Stev Stev       4 star  

                              Thanks a lot, I have passed 70-178 my test.

                              Leonard Leonard       4.5 star  

                              Microsoft certification examinations are hard to pass. If I do not purchase exam dumps I may not pass the exam. Luckily I made the right choice.

                              Stan Stan       4.5 star  

                              We appreciate all what you have done.for the dump 70-178

                              Henry Henry       4.5 star  

                              LEAVE A REPLY

                              Your email address will not be published. Required fields are marked *

                              Quality and Value

                              VerifiedDumps Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

                              Tested and Approved

                              We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

                              Easy to Pass

                              If you prepare for the exams using our VerifiedDumps testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

                              Try Before Buy

                              VerifiedDumps offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.

                              Our Clients