NEW QUESTION # 49
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
- A. 36 lifts
- B. 30 lifts
- C. 48 lifts
- D. 24 lifts
Answer: A
NEW QUESTION # 50
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
- A. Use the progressed portion of the critical path of all the updates previous to the current update.
- B. Use the forward-looking critical path of the most current updates.
- C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
- D. Use the progressed portion of the critical path of the baseline schedule.
Answer: B
NEW QUESTION # 51
Determine the correct formula and date for the late finish for Activity 9004.
- A. LS.10002^ Lag.7 + i day -> 11-20-03.
- B. LS.10002 - Lag.7 - l day -> 11-20-03.
- C. LS.10002 + 1 day -> 11-29-03.
- D. LS.10002 - 1 day -> 11-27-03.
Answer: A
NEW QUESTION # 52
Activity C is a
- A. Continuous activity.
- B. Contentious activity.
- C. Milestone.
- D. 1-day activity.
Answer: C
NEW QUESTION # 53
Which of the following will always describe the critical path? The path with
- A. Zero float.
- B. Negative float.
- C. The shortest duration and negative float.
- D. The longest duration through the network.
Answer: A
NEW QUESTION # 54
What is the remaining work duration of Active D?
- A. 0
- B. 3.
- C. 4.
- D. 8.
Answer: C
NEW QUESTION # 55
Project schedules help control all of the following EXCEPT for_____________________.
- A. Resources
- B. Cost
- C. Quality
- D. Time
Answer: C
NEW QUESTION # 56
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 5 days.
- B. 0 days.
- C. 15 days.
- D. 10 days.
Answer: A
NEW QUESTION # 57
If Activity E's duration changes to 4 months, what is the overall duration of the project.
- A. 21 months.
- B. 22 months.
- C. 20 months.
- D. 19 months.
Answer: C
NEW QUESTION # 58
These are the activities on the critical path:
- A. A, D, & I.
- B. A, B, F, & J
- C. A, B, G, & H.
- D. A, C, E, & H.
Answer: C
NEW QUESTION # 59
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
- A. Detailed listing of working days for each calendar used
- B. Tabular listing of activities showing duration, calendar ID, early and late dates
- C. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID
- D. Assigned party responsibility for each work task
Answer: D
NEW QUESTION # 60
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?
- A. Critical path schedules prepared by you for similar completed projects.
- B. Industry publications.
- C. The Petrochemical Industry New Plant Task Duration Handbook.
- D. The cost estimate for the plant prepared by your firm's estimating department.
Answer: A
NEW QUESTION # 61
Budgeted cost of work scheduled is _______________________.
- A. The value of the completed work expressed in terms of the budget assigned to that work
- B. The sum of all budgets for work scheduled to be accomplished within a given time period
- C. The total authorized budget for accomplishing the project scope
- D. The expected total cost of an activity, group of activities or the project
Answer: D
NEW QUESTION # 62
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
- A. The delay must not cause monetary harm to the defendant.
- B. The delay must be concurrent with the delay attributable to both parties.
- C. The delay must affect the critical path.
- D. The delay must affect the contractor's planned construction schedule.
Answer: C
NEW QUESTION # 63
Which of the following phases does NOT describe the commonly accepted construction life cycle?
- A. Claims and disputes phase.
- B. Installation phase.
- C. Turnover and start-up phase.
- D. Planning and design phase.
Answer: D
NEW QUESTION # 64
What method offers the best chance of the schedule being used effectively to implement the project in the field?
- A. Include detailed and stringent set of scheduling specifications in the contract.
- B. Allow large time contingencies on milestones and completion deadlines.
- C. Obtain consent and agreement to the schedule from the key project personnel.
- D. Issue detailed schedule updates as frequently as possible.
Answer: C
NEW QUESTION # 65
Project delays are best analyzed
- A. By an expert after the project is finished when complete records are available and the impact is known.
- B. After either the contractor or the owner acknowledges ^responsibility for the delay.
- C. Contemporaneously with the delay.
- D. Late in the project.
Answer: A
NEW QUESTION # 66
What is a key first step in developing a critical path method schedule?
- A. Drawing the logic diagram.
- B. Defining the execution plan to meet the required scope of work.
- C. Setting out the resource to be used and its limitations.
- D. Drawing a bar chart of the key phrases of the work.
Answer: A
NEW QUESTION # 67
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?
- A. Cannot be determined.
- B. 14.
- C. 13.
- D. 12.
Answer: D
NEW QUESTION # 68
Why does activity 1001 have two successor activities?
- A. Because the late finish of 1001 and the late start of 7001 require two successors
- B. Because there are two defined logic paths for the work
- C. Because the duration of activities 2001, 2002 and 200.f require two successors
- D. Because the problem could not effectively work with only one successor
Answer: B
NEW QUESTION # 69
......