Latest C_S4PPM_1909 exam dumps with real SAP questions and answers [Q15-Q35]

Share

Latest C_S4PPM_1909 exam dumps with real SAP questions and answers

C_S4PPM_1909 Exam in First Attempt Guaranteed


SAP C_S4PPM_1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA PPM Implementation Consultant profile. This certification proves that the candidate has an overall understanding and in‐depth technical skills to participate as a member of a project team in a mentored role. This certification exam is recommended as an entry level qualification.

 

NEW QUESTION 15
What is the priority field in the project definition of a project management project used for?

  • A. To determine the approval authorizations required
  • B. To determine the scheduled dates for the project
  • C. To support the evaluation of projects
  • D. To restrict the selection of project types

Answer: C

 

NEW QUESTION 16
What can you with roles in project management?
NOTE: There are 3 correct answers to this question

  • A. Define responsibilities for structure element
  • B. Define responsibilities for structure element
  • C. Define authorizations for reporting
  • D. Define decision makers for an approval process
  • E. Enable resource management

Answer: B,D,E

 

NEW QUESTION 17
When you confirm a task, you wants the system to calculate the difference between planned work and actual work.
What must you do?

  • A. Set the task status to in process
  • B. Confirm the task using a completion percentage of less than 100
  • C. Enter an actual finish date of the task in the future
  • D. Ensure that the Rem. Work manually indicator is inactive

Answer: D

 

NEW QUESTION 18
When is Bottom-up scheduling mandatory?

  • A. When parallel phasing is used
  • B. When actual time are recorded
  • C. When summary tasks are used
  • D. When constraints are used

Answer: C

 

NEW QUESTION 19
You are in portfolio management and create a project system (PS) project from an item.
Which parts you add afterwards directly in PS?
NOTE: There are 3 correct answers to this question

  • A. Network components
  • B. PS texts
  • C. WBS elements
  • D. Documents
  • E. Network activities

Answer: B,D,E

 

NEW QUESTION 20
What must you configure to view portfolio item data in project management projects?

  • A. Set the objects link flag to active in customizing for the project management structure
  • B. Set the portfolio management flag to active in customizing for the project type
  • C. Set the project management flag to active in customizing for the linking item type
  • D. Set the business content data source for portfolio management in customizing

Answer: B

 

NEW QUESTION 21
Which of the following multi-currency scenario are supported?
NOTE: There are 2correct answers to this question

  • A. Bucket in a portfolio can use different currencies
  • B. Item currency can be inherited from the assigned bucket
  • C. Items In a bucket an only use bucket currencies
  • D. Multiple planning currencies can be used in one bucket

Answer: A,B

 

NEW QUESTION 22
Which data is transferred when you import a Microsoft project management?

  • A. Cost
  • B. Task
  • C. Authorizations
  • D. Status reports

Answer: B

 

NEW QUESTION 23
You have created a portfolio with the bucket levels and wants to create a portfolio item.
When can you create the portfolio item?

  • A. At the highest bucket level
  • B. At multiple bucket levels
  • C. At any bucket level
  • D. At the lowest bucket level

Answer: D

 

NEW QUESTION 24
Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question

  • A. Phase
  • B. Task
  • C. Role
  • D. Checklist item

Answer: B,C

 

NEW QUESTION 25
Which information can be assigned to a business partner in project management?
NOTE: There are 3 correct answers to this question

  • A. Areas and locations
  • B. Production resources or tools (PRT)
  • C. SAP users
  • D. Work centers
  • E. Personal numbers

Answer: A,C,E

 

NEW QUESTION 26
Bucket A contains items and current located in bucket P1.
How do you move bucket A including the items to bucket p2.

  • A. Select bucket p2 in the move function as a target for bucket A
    Execute the move function
  • B. Select bucket A from the bucket dashboard
    Change the parent bucket field from P1 to P2
  • C. Move all items from bucket A to bucket p2.
    Move the empty bucket A to p2
    Copy all bucket A items from bucket p2 to bucket A
  • D. Create a new bucket in bucket P2
    Move all items from bucket A to the new bucket
    Delete bucket A and rename the new bucket

Answer: D

 

NEW QUESTION 27
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing?
NOTE: There are 2correct answers to this question

  • A. The Release Success phase only after Approval indicator
  • B. The approval phase indicator
  • C. The complete phase when Granting Approval indicator
  • D. The completion required indicator

Answer: A,B

 

NEW QUESTION 28
What is the PR/PLAN_INI_PREP report used for?

  • A. To transfer costs from accounting objects to PPM
  • B. To create financial and capacity categories and groups based on customizing
  • C. To transfer recoded time from CATS to PPM
  • D. To upload financial data from Microsoft Excel

Answer: B

 

NEW QUESTION 29
No upcoming milestone are shown in the my projects SAP Fiori app.
What are the reasons for this?
NOTE: There are 2correct answers to this question

  • A. Project is not released
  • B. You are not defined as the project Responsible
  • C. Milestone is not identified as mandatory
  • D. Milestone is not identified ascritical

Answer: A,B

 

NEW QUESTION 30
Which of the following object help to support automatic creation between portfolio and project management (PPM) and project system (PS)?
NOTE: There are 2correct answers to this question

  • A. PS standard project
  • B. PS network
  • C. PS profile
  • D. PS operative project

Answer: C,D

 

NEW QUESTION 31
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?

  • A. Enable the split of financial values for the item type.
    *Assign the item to two bucket of the classification hierarchy
    *Maintain factors to split financial planning of the item
  • B. Enable financial planning for multiple buckets
    *Assign additional buckets in financial planning
    *Maintain factors to split financial planning of the item.
  • C. Enable the split of financial values for the item type
    *Assign the item to two bucket of the portfolio
    *Maintain factors to split financial planning of the item
  • D. Enable process change for multiple buckets.
    *Start process change to reassign the item two buckets
    *Maintain factors to split financial planning of the item

Answer: A

 

NEW QUESTION 32
What must you do before you can use multiple currencies in financial planning in portfolio management?

  • A. Define a subnet of currencies in project system
  • B. Select multiple currencies in the portfolio item
  • C. Define a subnet of currencies in portfolio and project management
  • D. Select multiple currencies in the portfolio definition

Answer: A

 

NEW QUESTION 33
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2correct answers to this question

  • A. Staffing manager assignment is missing
  • B. Project response assignment
  • C. Resource pool assignment is missing
  • D. Assignment of resource management authorization object is missing

Answer: A,C

 

NEW QUESTION 34
What is a prerequisite for using role charts in project management?

  • A. A graphic profile is assigned to the role type
  • B. The demand of a role must be distributed over a number of periods
  • C. The demand of a role must have been updated according to tasks
  • D. A graphic profile is assigned to the project type

Answer: B

 

NEW QUESTION 35
......


C_S4PPM_1909 Exam Certification Details:

Cut Score:57%
Duration:180 mins
Level:Associate

 

Exam Sure Pass SAP Certification with C_S4PPM_1909 exam questions: https://www.verifieddumps.com/C_S4PPM_1909-valid-exam-braindumps.html