NEW QUESTION # 30
How can you achive a feasible production plan in case of capacity constraints?
- A. Form optimum sequence to reduce setup times
- B. Select an alternative mode on a resource.
- C. Execute an infinite production planning run
- D. Adjust the available capacity.
- E. Reduce the planning window
Answer: A,B,D
NEW QUESTION # 31
In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?
- A. MRP type
- B. MRP planning file
- C. MRP controller
- D. MRP group
Answer: C
NEW QUESTION # 32
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
- A. Production order release
- B. Kanban
- C. Backflushing
- D. Material requirements planning
Answer: D
NEW QUESTION # 33
What is the purpose of a reporting point confirmation in repetitive manufacturing?
- A. To determine the work in progress along the production line
- B. To provide timely updates of inventory management for the staged components
- C. To stage different components for a production line simultaneously
- D. To reduce the total production lead time for along production line
Answer: A,B
NEW QUESTION # 34
You want to schedule an operation finitely, without moving other operations. Which scheduing strategy do you select?
- A. Find slot
- B. Insert operation
- C. Squeeze in
- D. Schedule in working time only
Answer: A
NEW QUESTION # 35
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Replenishment strategy
- B. Control cycle
- C. Production supply area
- D. Rate routing
Answer: B
NEW QUESTION # 36
Why would you use phantom assemblies?
- A. To reduce the number of changes required in bills of materials
- B. To reduce the number of material masters
- C. To simplify the structure of bills of materials
- D. To increase the number of planning levels
- E. To make the assignment of components easier
Answer: A,C,E
NEW QUESTION # 37
Which business processes are affected by setting in the order type-dependent parameters?
- A. Implement engineering changes.
- B. Define integration to cost accounting.
- C. Select master data.
- D. Intiate quality inspections.
Answer: B,C
NEW QUESTION # 38
How can you carry out cost object controlling for production orders?
- A. Product-related
- B. Order-related
- C. Cost-related
- D. Milestone-related
Answer: A,B
NEW QUESTION # 39
In the Schedule Production app which setting can you make for the planning strategy?
- A. Fitness level
- B. Planning mode
- C. Scheduling control
- D. Direction
- E. Fixed pegging
Answer: B,C,D
NEW QUESTION # 40
Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA?
- A. By usage probability
- B. Simultaneous
- C. 100% check
- D. First in first out (FIFO)
Answer: A,C
NEW QUESTION # 41
Which of the following elements does MRP take into account during net requirement calculation?
- A. Maximum stock level
- B. Purchase orders
- C. Safety stock
- D. Lot size
Answer: C,D
NEW QUESTION # 42
What could be the reason for multiple commitment of invidula capacities, where several operations have the same scheduled dates on a work center (or resource) after planing?
- A. The finite Scheduling indicator is NOT set in the strategy profile.
- B. Alternative work centers are fully occupied.
- C. The work center has several invidula capacities.
- D. The Change Planning Direction indicator is set in strategy profile.
Answer: A,C
NEW QUESTION # 43
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?
- A. SAP Hybris
- B. SAP Ariba
- C. SAP Concur
- D. SAP SuccessFactors
- E. SAP Fieldglass
Answer: B,C,E
NEW QUESTION # 44
Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?
- A. Reduction of associated capacity requirements
- B. Archiving of documents for assembly scrap
- C. Posting of production costs to the production cost collector
- D. Material staging for nex order in sequence
- E. Posting of goods receipt for the product
Answer: A,C,E
NEW QUESTION # 45
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?
- A. Fill up to the maximum stock level
- B. Fill up based on the lot size procedure
- C. Fill up to the reorder stock level
- D. Fill up to the safety stoc level
Answer: B
NEW QUESTION # 46
You want to create a production order from a planned order. What methods could you use?
- A. Order release
- B. Collective conversion
- C. Partial conversion
- D. Combined conversion
Answer: B,C
NEW QUESTION # 47
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?
- A. Planning with final assembly (40)
- B. Make-to-order production (20)
- C. Make-to-stock production (10)
- D. Planning without final assembly (50)
Answer: A
NEW QUESTION # 48
Where do you maintain the work center that represents the production line for repetitive manufacturing?
- A. Repetitive manufacturing profile
- B. Production cost collector
- C. Production version
- D. Routing
Answer: C,D
NEW QUESTION # 49
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
- A. Make-to-order production (20)
- B. Planning with final assembly (40)
- C. Planning without final assembly (50)
- D. Planning at assembly level (70)
Answer: C
NEW QUESTION # 50
Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing.
What is the impact of this decision?
- A. A sales-order-specific planning run is required.
- B. Production orders specific stock is created
- C. Storage location MRP areas are required.
- D. Net requirement calcualtion is sales-order specific.
Answer: A,B,D
NEW QUESTION # 51
How would you define pegging in the context of Advanced Planning?
- A. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements
- B. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements
- C. An evaluation to verify if there are material or capacity shortages in the network after the production planning run.
- D. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run
Answer: B
NEW QUESTION # 52
......
SAP C_TS422_2021 certification exam is a comprehensive assessment of an individual's skills and knowledge in the field of SAP S/4HANA Production Planning and Manufacturing. SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 certification is a valuable asset for professionals who want to enhance their career prospects in this field and demonstrate their expertise to the employers. SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 certification exam covers a wide range of topics related to SAP S/4HANA Production Planning and Manufacturing and requires candidates to demonstrate their proficiency in various areas such as production planning, material requirements planning, capacity planning, and shop floor control.
SAP C-TS422-2021 Certification Exam is a valuable credential for professionals who work in production planning and manufacturing. SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 certification demonstrates that the individual has the knowledge and skills necessary to design, configure, and implement SAP S/4HANA Production Planning and Manufacturing solutions. It also shows that the individual is committed to staying up-to-date with the latest industry standards and best practices.
Latest C_TS422_2021 Pass Guaranteed Exam Dumps Certification Sample Questions: https://www.verifieddumps.com/C_TS422_2021-valid-exam-braindumps.html
C_TS422_2021 Exam with Guarantee Updated 82 Questions: https://drive.google.com/open?id=1gElNK3OidhpkTaVfbZ38fwe6uZfa-aYk